January 2024 Update
Turtle Creek Station’s substation has been completed and energized in November.
For the generation part of the site, all the major equipment is on site, construction activities continue, and the site is preparing for commissioning in the coming months. During the commissioning process, OPPD works with its construction contractors and turbine manufacturers to ensure all systems are working properly and the facilities are ready to produce energy.
The lighting and paving work is underway, along with beautification and other cosmetic work. Also coming in 2024 will be site landscaping work.
Turtle Creek Station is scheduled to come online late this summer, for more highlights of recent progress, please see this story in The Wire.