Turtle Creek Station

Share Turtle Creek Station on Facebook Share Turtle Creek Station on Twitter Share Turtle Creek Station on Linkedin Email Turtle Creek Station link


Aerial View of Turtle Creek Station - October 2024


For the latest happenings at the Turtle Creek Station site location, please see the News Feed at the bottom of this page.


OPPD' s Power with Purpose project identified the need for up to 600MW of utility-scale solar and 600MW of balancing natural gas generation to support growing customer demands. The combined solution of utility-scale solar and natural gas continues to support our mission of providing affordable, reliable, environmentally sensitive energy services. While OPPD considers all three parts of our mission equally, new utility-scale solar and balancing natural gas power generation are now must-haves to support continued reliability. Turtle Creek Station is one of this initiative’s balancing natural gas plants.

In 2023, the OPPD Board of Directors voted to approve the utility’s recommended near term generation resource plan to address unprecedented growth in energy demand. With this new plan, OPPD remains committed to its Power with Purpose generation expansion projects, which includes Turtle Creek Station (450 MW), Standing Bear Lake Station (150 MW), and Platteview Solar (81 MW).

Turtle Creek Station will be located near South 168th Street and Fairview Road in Sarpy County. It will include two, simple-cycle combustion turbines and supporting structures for generation, along with a substation for transmission.

Turtle Creek Station will be used to balance the energy load. The plant will run only as needed (estimated at less than 15% of the time) and will be available to support planned (maintenance) and unplanned (storms) outages, as well as be available to support regional power needs as directed by the Southwest Power Pool. Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and support resiliency. That means OPPD can continue providing energy to our customers even in an unpredictable future. Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and will support resiliency. That means OPPD can continue providing energy to our customers even when operations are impacted by a major storm event.

Combustion Turbines

OPPD selected Siemens Energy, Inc. to provide two, SGT6-5000F combustion turbines to power Turtle Creek Station, a simple-cycle turbine facility. The turbine technology converts natural gas into energy to drive a generator, which produces electricity.

Modern natural gas turbines from Siemens Energy, Inc. are designed to also run on light fuel oil, adding fuel source diversity and resiliency. And they are capable of running on a 30% hydrogen/natural gas blend or biodiesel in support of future technology advancements to further decarbonization of OPPD’s generation assets. The turbines offer low emissions that help OPPD meet its targets without the need for additional air pollution control devices. They also have improved operational characteristics, such as fast start-up to supplement renewable energy and meet the changing generation needs of the grid.

Sarpy Southwest Transmission Project

OPPD has completed routing three separate transmission lines in the area that are needed to maintain system resiliency and reliability, as well as to support customer load growth and future power generation. The Sarpy Southwest Transmission Project is now currently under construction. For more information and to see the transmission line routes, please click here.

Additional Site Information

Community Meeting: South 168th & Fairview Road

OPPD The Wire: New facility names reflect history, geography of region

OPPD The Wire: OPPD presents details of new backup natural gas generation

OPPD The Wire: OPPD signs contract for two natural gas generation stations

OPPD The Wire: Work progressing at natural gas sites

OPPD The Wire: OPPD seeks to extend current operations at North Omaha Station

OPPD The Wire: Two natural gas generating plants set to come online this summer



Aerial View of Turtle Creek Station - October 2024


For the latest happenings at the Turtle Creek Station site location, please see the News Feed at the bottom of this page.


OPPD' s Power with Purpose project identified the need for up to 600MW of utility-scale solar and 600MW of balancing natural gas generation to support growing customer demands. The combined solution of utility-scale solar and natural gas continues to support our mission of providing affordable, reliable, environmentally sensitive energy services. While OPPD considers all three parts of our mission equally, new utility-scale solar and balancing natural gas power generation are now must-haves to support continued reliability. Turtle Creek Station is one of this initiative’s balancing natural gas plants.

In 2023, the OPPD Board of Directors voted to approve the utility’s recommended near term generation resource plan to address unprecedented growth in energy demand. With this new plan, OPPD remains committed to its Power with Purpose generation expansion projects, which includes Turtle Creek Station (450 MW), Standing Bear Lake Station (150 MW), and Platteview Solar (81 MW).

Turtle Creek Station will be located near South 168th Street and Fairview Road in Sarpy County. It will include two, simple-cycle combustion turbines and supporting structures for generation, along with a substation for transmission.

Turtle Creek Station will be used to balance the energy load. The plant will run only as needed (estimated at less than 15% of the time) and will be available to support planned (maintenance) and unplanned (storms) outages, as well as be available to support regional power needs as directed by the Southwest Power Pool. Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and support resiliency. That means OPPD can continue providing energy to our customers even in an unpredictable future. Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and will support resiliency. That means OPPD can continue providing energy to our customers even when operations are impacted by a major storm event.

Combustion Turbines

OPPD selected Siemens Energy, Inc. to provide two, SGT6-5000F combustion turbines to power Turtle Creek Station, a simple-cycle turbine facility. The turbine technology converts natural gas into energy to drive a generator, which produces electricity.

Modern natural gas turbines from Siemens Energy, Inc. are designed to also run on light fuel oil, adding fuel source diversity and resiliency. And they are capable of running on a 30% hydrogen/natural gas blend or biodiesel in support of future technology advancements to further decarbonization of OPPD’s generation assets. The turbines offer low emissions that help OPPD meet its targets without the need for additional air pollution control devices. They also have improved operational characteristics, such as fast start-up to supplement renewable energy and meet the changing generation needs of the grid.

Sarpy Southwest Transmission Project

OPPD has completed routing three separate transmission lines in the area that are needed to maintain system resiliency and reliability, as well as to support customer load growth and future power generation. The Sarpy Southwest Transmission Project is now currently under construction. For more information and to see the transmission line routes, please click here.

Additional Site Information

Community Meeting: South 168th & Fairview Road

OPPD The Wire: New facility names reflect history, geography of region

OPPD The Wire: OPPD presents details of new backup natural gas generation

OPPD The Wire: OPPD signs contract for two natural gas generation stations

OPPD The Wire: Work progressing at natural gas sites

OPPD The Wire: OPPD seeks to extend current operations at North Omaha Station

OPPD The Wire: Two natural gas generating plants set to come online this summer

  • November 2024 Update

    Share November 2024 Update on Facebook Share November 2024 Update on Twitter Share November 2024 Update on Linkedin Email November 2024 Update link

    Turtle Creek Station is beginning to turn the corner from construction to operations. During the week of Nov. 4, a major milestone called “first fire” is taking place. The exact date and time first fire will take place has some fluidity, with many moving pieces that should take place by the end of this week. We are currently on track for first fire to take place on Thursday, November 7th or Friday, November 8th. During this first fire, the gas turbine, Unit 1, is brought up to operational speed, essentially becoming capable of generating electricity, using natural gas as fuel.

    Close neighbors or passersby may see some visible gray smoke coming out of the stack exhaust at the plant during this time. The smoke is caused by the burn-off of coating, dust or other debris in the piping. As the generating units are tested and tuned, exhaust will become much less noticeable. It will dissipate within approximately 15-minutes. While first fire can be noisy inside the plant, we do not expect the noise to be noticeable outside the plant.

    The unit will then run on natural gas for about 22 days, generating electricity at different levels for testing. Then it will shut down for several weeks before coming back online, but with diesel fuel oil. This will result in another start-up process that will take place at Turtle Creek Station, but with fuel oil, in early December.

    Unit 2, which is currently nearing the end of construction, is scheduled to begin its first-fire process shortly after Unit 1 – within the window that Unit 1 is running on natural gas.

    We are excited about this next big step as we grow and diversify our generation resources to keep reliable, resilient power flowing to our customers.

  • August 2024 Update

    Share August 2024 Update on Facebook Share August 2024 Update on Twitter Share August 2024 Update on Linkedin Email August 2024 Update link

    Deliveries of commodities needed for Turtle Creek Station continue as construction moves closer to the end and towards an operational site. Please be aware of extra truck traffic entering and exiting along Fairview Road at the site entrance, and continuing along S. 168 St and Platteview Road.

    OPPD will treat Fairview Road in effort to reduce dust created from these deliveries.

  • July 2024 Update

    Share July 2024 Update on Facebook Share July 2024 Update on Twitter Share July 2024 Update on Linkedin Email July 2024 Update link

    Construction continues at Turtle Creek Station with progress nearing 90% completion. Equipment startup and commissioning activities have ramped up and are in full swing. Landscaping work is also well under way as more than 350 new trees and shrubs will be planted near and around the facility. Key activities planned for August include continued equipment startup and commissioning, moving furniture and other equipment into the administration building and preparation for fuel deliveries.

  • March 2024 Update

    Share March 2024 Update on Facebook Share March 2024 Update on Twitter Share March 2024 Update on Linkedin Email March 2024 Update link

    With site progress at about 82%, construction activities are ramping up ahead of commissioning as the generation facility is scheduled to go online later this year. As the crews works diligently to meet this deadline, shifts will continue into the night at times as we approach operation. Night shifts are expected to have smaller crews and will adhere to all permits and ordinances necessary.

  • February 2024 Update

    Share February 2024 Update on Facebook Share February 2024 Update on Twitter Share February 2024 Update on Linkedin Email February 2024 Update link

    OPPD announced plans to add a total of four combustion turbines capable of producing 225 MW each – three at OPPD’s Cass County plant and one at Turtle Creek Station. The new units are expected be online by 2030. For more information, please see this story in The Wire.

    Siemens was selected to manufacture the units, and the units will be the same as the combustion turbines at Turtle Creek Station today.


  • January 2024 Update

    Share January 2024 Update on Facebook Share January 2024 Update on Twitter Share January 2024 Update on Linkedin Email January 2024 Update link


    TCS Aerial January 2024 – Facing Southeast

    Turtle Creek Station’s substation has been completed and energized in November.

    For the generation part of the site, all the major equipment is on site, construction activities continue, and the site is preparing for commissioning in the coming months. During the commissioning process, OPPD works with its construction contractors and turbine manufacturers to ensure all systems are working properly and the facilities are ready to produce energy.

    The lighting and paving work is underway, along with beautification and other cosmetic work. Also coming in 2024 will be site landscaping work.

    Turtle Creek Station is scheduled to come online late this summer, for more highlights of recent progress, please see this story in The Wire.

  • September 2023 Update

    Share September 2023 Update on Facebook Share September 2023 Update on Twitter Share September 2023 Update on Linkedin Email September 2023 Update link

    Beginning Sunday, Oct. 1, and again on Sunday, Oct 8, specialized large-equipment movers on behalf of Omaha Public Power District will move two Generator Step-up (GSU) Transformers to the Turtle Creek Station site at 168th & Fairview Rd. in Sarpy County.

    A GSU transformer is designed to step-up generator output to a higher voltage that’s ready to connect to the transmission network.

    Just one of these transformers, loaded on a trailer, weighs about 437,500 pounds. Together, the truck and trailer set-up measures 311-feet long and weighs 879,200 pounds. The transformer equipment arrives to our area by rail before being loaded on a trailer for the final leg of its journey to the new plant.

    The work to move the units to Turtle Creek Station is scheduled at night to ensure minimal traffic disruption, as brief road closures may be needed. OPPD and our contracted large-equipment movers have coordinated with city, county, and state officials, as well as members of law enforcement, to ensure the safety of the public and workers along the route.

    If members of the public come across this move, we ask that they refrain from approaching employees, contractors or vehicles and stay far back from the work taking place so that we can complete it safely.

  • July 2023 Update

    Share July 2023 Update on Facebook Share July 2023 Update on Twitter Share July 2023 Update on Linkedin Email July 2023 Update link

    Above ground construction at Turtle Creek Station is well underway. Overall assembly of units 1 & 2 combustion turbines and respective stack formation are making visual progress. Additionally, the power distribution center has been set. The substation is now nearing final stages of construction.

    Facing Southwest, Aerial View, June 2023

  • May 2023 Update

    Share May 2023 Update on Facebook Share May 2023 Update on Twitter Share May 2023 Update on Linkedin Email May 2023 Update link

    A lot of construction progress has been happening on site the last few months as seen in this aerial photo. Recent focus has been on major equipment assembly and the administrative building.

    Major transmission work is complete, which will connect Turtle Creek Station to the electric grid. Additional transmission work will take place in the fall to coordinate energization.

    Facing North – Construction Progress as of April 2023

  • February 2023 Update

    Share February 2023 Update on Facebook Share February 2023 Update on Twitter Share February 2023 Update on Linkedin Email February 2023 Update link

    Construction progresses during the winter months for the substation at Turtle Creek Station with concrete duct bank pours, ground grid installation, and steel support erection underway.

    The administration building walls are going up with framing activities subsequently following.

    In the generation or power block area, both sets of Siemens Energy gas turbines and generators were placed on their foundation last month.


    Facing North - Substation Construction Progress

Page last updated: 07 Nov 2024, 12:24 PM