Standing Bear Lake Station

Share Standing Bear Lake Station on Facebook Share Standing Bear Lake Station on Twitter Share Standing Bear Lake Station on Linkedin Email Standing Bear Lake Station link

Aerial View of Standing Bear Lake Station - Oct. 2024

For the latest happenings at the Standing Bear Lake Station site location, please see the News Feed at the bottom of this page.



OPPD's Power with Purpose project identified the need for up to 600MW of utility-scale solar and 600MW of balancing natural gas generation to support growing customer demands. The combined solution of utility-scale solar and natural gas continues to support our mission of providing affordable, reliable, environmentally sensitive energy services. While OPPD considers all three parts of our mission equally, new utility-scale solar and balancing natural gas power generation are now must-haves to support continued reliability.

In 2023, the OPPD Board of Directors voted to approve the utility’s recommended near term generation resource plan to address unprecedented growth in energy demand. With this new plan, OPPD remains committed to its Power with Purpose generation expansion projects, which includes Turtle Creek Station (450 MW), Standing Bear Lake Station (150 MW), and Platteview Solar (81 MW).

Standing Bear Lake Station will be located near North 120th Street and Military Road. It will include nine reciprocating engines for generation, along with a substation for transmission.

Standing Bear Lake Station will be used to balance the energy load. The plant will run only as needed (estimated at less than 15% of the time) and will be available to support planned (maintenance) and unplanned (storms) outages, as well as be available to support regional power needs as directed by the Southwest Power Pool. Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and support resiliency. That means OPPD can continue providing energy to our customers even in an unpredictable future.

Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and support resiliency. That means OPPD can continue providing energy to our customers even when operations are impacted by a major storm event.

Reciprocating Internal Combustion Engines (RICE)

The utility has selected nine Wärtsilä 18V50DF reciprocating internal combustion engines (RICE) to power OPPD’s new Standing Bear Lake Station in northwest Omaha.

RICE technology converts natural gas into energy to drive a generator, which produces electricity. These natural gas internal combustion engines Wärtsilä will provide can also run on light fuel oil, adding fuel flexibility.

The engines are capable of running on a 15% hydrogen/natural gas blend in support of future technology advancements. RICE engines offer fast start-up to rapidly address the influx of renewables and the changing generation needs of the electrical grid.



Preliminary Map

This preliminary and conceptual map shows the layout of the Standing Bear Lake Station site as of November 2021. The map outlines where the new natural gas generation peaking station and substation may be located. The existing cell phone tower has been removed and a new permanent cell tower will be placed on the M.U.D. property. The map also shows the area on the northwest triangle of the property will be used to support construction staging through the project duration only.

Additional Site Information

Community Meeting: North 120th & Military Road

OPPD The Wire: New facility names reflect history, geography of region

OPPD The Wire: OPPD presents details of new backup natural gas generation

OPPD The Wire: OPPD signs contract for two natural gas generation stations

RambleRidge Neighborhood Homeowners Association: Nov. 2021 Presentation

OPPD The Wire: Work progressing at natural gas sites

OPPD The Wire: OPPD seeks to extend current operations at North Omaha Station

OPPD The Wire: Video: Massive engines mark a Power with Purpose milestone

OPPD The Wire: Two natural gas generating plants set to come online this summer

Aerial View of Standing Bear Lake Station - Oct. 2024

For the latest happenings at the Standing Bear Lake Station site location, please see the News Feed at the bottom of this page.



OPPD's Power with Purpose project identified the need for up to 600MW of utility-scale solar and 600MW of balancing natural gas generation to support growing customer demands. The combined solution of utility-scale solar and natural gas continues to support our mission of providing affordable, reliable, environmentally sensitive energy services. While OPPD considers all three parts of our mission equally, new utility-scale solar and balancing natural gas power generation are now must-haves to support continued reliability.

In 2023, the OPPD Board of Directors voted to approve the utility’s recommended near term generation resource plan to address unprecedented growth in energy demand. With this new plan, OPPD remains committed to its Power with Purpose generation expansion projects, which includes Turtle Creek Station (450 MW), Standing Bear Lake Station (150 MW), and Platteview Solar (81 MW).

Standing Bear Lake Station will be located near North 120th Street and Military Road. It will include nine reciprocating engines for generation, along with a substation for transmission.

Standing Bear Lake Station will be used to balance the energy load. The plant will run only as needed (estimated at less than 15% of the time) and will be available to support planned (maintenance) and unplanned (storms) outages, as well as be available to support regional power needs as directed by the Southwest Power Pool. Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and support resiliency. That means OPPD can continue providing energy to our customers even in an unpredictable future.

Adding natural gas generation will help OPPD meet the growing energy needs of our service territory and support resiliency. That means OPPD can continue providing energy to our customers even when operations are impacted by a major storm event.

Reciprocating Internal Combustion Engines (RICE)

The utility has selected nine Wärtsilä 18V50DF reciprocating internal combustion engines (RICE) to power OPPD’s new Standing Bear Lake Station in northwest Omaha.

RICE technology converts natural gas into energy to drive a generator, which produces electricity. These natural gas internal combustion engines Wärtsilä will provide can also run on light fuel oil, adding fuel flexibility.

The engines are capable of running on a 15% hydrogen/natural gas blend in support of future technology advancements. RICE engines offer fast start-up to rapidly address the influx of renewables and the changing generation needs of the electrical grid.



Preliminary Map

This preliminary and conceptual map shows the layout of the Standing Bear Lake Station site as of November 2021. The map outlines where the new natural gas generation peaking station and substation may be located. The existing cell phone tower has been removed and a new permanent cell tower will be placed on the M.U.D. property. The map also shows the area on the northwest triangle of the property will be used to support construction staging through the project duration only.

Additional Site Information

Community Meeting: North 120th & Military Road

OPPD The Wire: New facility names reflect history, geography of region

OPPD The Wire: OPPD presents details of new backup natural gas generation

OPPD The Wire: OPPD signs contract for two natural gas generation stations

RambleRidge Neighborhood Homeowners Association: Nov. 2021 Presentation

OPPD The Wire: Work progressing at natural gas sites

OPPD The Wire: OPPD seeks to extend current operations at North Omaha Station

OPPD The Wire: Video: Massive engines mark a Power with Purpose milestone

OPPD The Wire: Two natural gas generating plants set to come online this summer

  • July 2023 Update

    Share July 2023 Update on Facebook Share July 2023 Update on Twitter Share July 2023 Update on Linkedin Email July 2023 Update link

    Above ground construction at Standing Bear Lake Station is well underway. All Wartsila engines and generators have been moved into the Engine Hall. The exhaust ducts and stacks are being constructed and installed. Additionally, the substation is nearing the final stages of construction.

    Facing South, Aerial View, June 2023

  • May 2023 Update

    Share May 2023 Update on Facebook Share May 2023 Update on Twitter Share May 2023 Update on Linkedin Email May 2023 Update link

    A lot of construction progress has been happening on site the last few months as seen in this aerial photo.

    In mid-May, the nine Wartsila engines and generators (seen in blue) will be moved to the new engine hall.

    Foundations for the transmission lines have been set along Military Road. Transmission work will be completed this fall in coordination with the energization of the substation onsite.

    Facing South – Substation and Generation Construction Progress as of April 2023

  • February 2023 Update

    Share February 2023 Update on Facebook Share February 2023 Update on Twitter Share February 2023 Update on Linkedin Email February 2023 Update link

    Construction progresses during the winter months with erection of the engine hall in the power block area and with erection of vertical bus supports in the substation area at Standing Bear Lake Station.

    The large temporary tent structure at the north of the site has been removed following assembly of the nine Wärtsilä engines. The associated generators have also been received. All three Generator Step-up Transformers (GSU) have been transported to the Standing Bear Lake Station site and are on their foundations.


    Facing South – Substation and Generation Construction Progress

  • December 2022 Update

    Share December 2022 Update on Facebook Share December 2022 Update on Twitter Share December 2022 Update on Linkedin Email December 2022 Update link

    Beginning Friday, Dec. 9, the first of three Generator Step-up Transformers (GSU) will be transported to the Standing Bear Lake Station site. The GSU transformer will step-up the generator output to a higher voltage to be put on the transmission network. The other two GSUs will be transported later this month.

    If members of the public come across this move, we ask that they refrain from approaching employees, contractors or vehicles and stay far back from the work taking place so that we can complete it safely.

  • November 2022 Update

    Share November 2022 Update on Facebook Share November 2022 Update on Twitter Share November 2022 Update on Linkedin Email November 2022 Update link

    Activity continues at the north end of the site near the entrance off Military Road where a large, temporary structure has been erected. OPPD’s vendor will be assembling equipment within that structure over the next few months.

    Transmission line work in the vicinity will be starting soon to help connect the new Standing Bear Lake Station and associated substation to the grid.


  • September 2022 Update

    Share September 2022 Update on Facebook Share September 2022 Update on Twitter Share September 2022 Update on Linkedin Email September 2022 Update link

    Beginning Sept. 6 and over the next couple of weeks, OPPD will be working with contractors to transport nine Wärtsilä reciprocating internal combustion engines to the Standing Bear Lake Station, near 114th Street and Military Road. One engine will be moved at a time, with activity occurring later in the evening and going into the overnight hours.

    Specialized large equipment movers will be utilized for this effort. Loaded on a trailer, the equipment measures approximately 248’ long by 14’ wide and 19’ tall. The trailer and engine combined will weigh in at 796,000 pounds. These engines were shipped from Italy and then shipped by rail to Nebraska.

    Such a massive move will require some road closures for a brief period of time overnight as the equipment travels along its journey. OPPD and the large equipment movers have coordinated with city, county and state officials, as well as members of law enforcement, to ensure the safety of the public and workers along the route.

    While such a big move will certainly pique interest, we ask that the public refrain from approaching employees, contractors or vehicles. Please stay a safe distance back, off of streets, so we can complete this important work. Obey all traffic signs and law enforcement officers, who will be stationed at various locations to assist in this process.

    Learn more and see video of the move here.

  • Summer 2022 Update

    Share Summer 2022 Update on Facebook Share Summer 2022 Update on Twitter Share Summer 2022 Update on Linkedin Email Summer 2022 Update link

    OPPD's vendor, Zachry Group, continues to prepare laydown and storage areas for equipment, materials, and supplies in anticipation of approaching construction work.

    A new entrance to the construction area is being placed east of the current entrance off Military Road.

    Preliminary grading is winding down and foundation work has begun in preparation for the new facility.

    This summer, construction activities will include work on gas and transmission infrastructure, although major equipment isn’t expected to arrive until late summer or early fall.


  • April 2022 Update

    Share April 2022 Update on Facebook Share April 2022 Update on Twitter Share April 2022 Update on Linkedin Email April 2022 Update link

    Grading is nearly complete where the new facility and substation will be located. M.U.D. has also begun installing a portion of gas pipeline at the site ahead of construction.

    In mid- to late-April you will notice some additional activity on the northwest corner of the M.U.D. property, near the intersection of 120th and Military. OPPD’s vendor, Zachry, will be using this area for temporary offices, storage of equipment, materials and supplies. Entrances to this area will be off 120th Street, so you may see additional traffic entering and exiting the property at this location. After construction, the area will be restored to its original condition.

    Over the next couple months and into the summer, Zachry will begin work on the associated substation and will begin construction on the natural gas plant. In late summer to early fall, transmission lines will be constructed to connect the new plant and substation to the power grid.

Page last updated: 13 Dec 2024, 09:47 AM