May 2023 Update

A lot of construction progress has been happening on site the last few months as seen in this aerial photo.

In mid-May, the nine Wartsila engines and generators (seen in blue) will be moved to the new engine hall.

Foundations for the transmission lines have been set along Military Road. Transmission work will be completed this fall in coordination with the energization of the substation onsite.

Facing South – Substation and Generation Construction Progress as of April 2023