Deliveries of commodities needed for Standing Bear Lake Station continue as construction moves closer to the end and towards an operational site. Please be aware of extra truck traffic entering and exiting along Military Road at the site entrance. Please note, this is a change as previously deliveries entered along 120th Street.

As we prepare the pipes and lines for use, air compressors are used to send a pressurized air blow through the system to clean it out. Most of the larger pipes have already been cleaned through pulsed air blows. Smaller lines will be blown out using continuous air blows to clean and dry the inside of the piping. This work continues through August but is not expected to be as loud and will be continuous, rather than pulsed, if heard or felt.